Hi Everyone,
First timer.
We need some help.
Unfortunately, we have to terminate our contract with our current builder.
They are over the contract completion date. Have not made reasonable communication and have not notified us of the new completion date.
We are currently at gyprock / lock up stage.
Has anyone been in this situation?
What are your suggestions?
Is it going to be 'cheaper' for us to try and find another builder to complete the work? or do we find individual trades people to assist us to finish if we get a builders permit?
We signed the contract 16 months ago
Slab poured 8 months ago
Currently at gyprock / lock up stage