Browse Forums Building A New House 1 Jul 02, 2013 1:06 pm We are building our first house and it has reched lock up stage Things that are still need to be done are: 1. Painting internal and external ( walls,cornices,ceiling,doors) 2. Vanities,tabs and kitchen appliances 3. Driveway 4. Concrete outside 5. garage door We are doing main flooring ourselves. Does anyone know how much roughly it will take to finish the above listed things ? Re: Time frame after Lock up stage 2Jul 02, 2013 1:24 pm Ours was just under 3 months. Built a Hawthorne 31 with EB nessjeffdreamhouse.blogspot.com.au Building an investment now with New Living homes... We are at nearly finished... Just landscaping and driveway to go! Re: Time frame after Lock up stage 4Jul 02, 2013 1:50 pm Its hard to say in months as onmy builds its taken from 2 -6 Months. I think its better to say "lock up is 1/2 way". The Harder You Try - the Luckier You Get ! Web site http://www.anewhouse.com.au Informative, Amusing, and Opinionated Blog - Over 600 posts on all aspects of building a new house. 1 4678 This is 100% true. You can not hang anything on steel frames. very frustrating 8 5354 Not unless you have managed to put it as a special condition into the contract somehow. 1 6150 |