Browse Forums Building A New House 1 Jun 25, 2013 6:07 pm Hi all I'm builing a double storey., I recently spotted that our 28c front entrance double door frame was 25c. The brickwork has already been complete for the ground floor (so the frame is in and brickwork completed above the frame). After I told them, the builder agreed there was an error and they had received the wrong door frame and the brickies had gone ahead and installed - the builder said they'd replace the frame and ground floor brickwork once the slab is poured and the second floor brickwork is started. IS this OK??! They assure me structurlaly it's fine to redo brickwork on the ground floor after slab... anyone with any knowledge whatsoever please advise what you think. I have no idea if I should be cool with this or not. Thank you @. Tried to play with the facade models but the exact colour is not matching up. 2 3230 Hi All, I engaged a tradie to install concrete retaining wall 600-800mm high over 32 meters in Victoria. Sleepers are 200*75*2000 mm installed over 17 steel posts. I… 0 6889 Building Standards; Getting It Right! Don't think they are designed for double brick. WA has a particular way of building and unfortunately that's the way a large amount of sills are finished. 3 6996 |