How long was your final stage?
Page 1 of 1
What work's being done during the final stage you're asking about?
Oh I didnt realise they were different classifications. On our final stage its:
Floor & Wall tiles
Brick Clean
Downpipes installed
Painting
Shower Screens
Mirrors
Door Knobs
Robe Doors & Shelving
Plumbing fit off
Electrical Fit off
Garage Door
Flyscreens
Carpet
Ducting Heating fit off
Ceiling installation
House clean
Final site clean
Removal Hire Items
Quality Assurance Assessment
Related
20/06/2023
9
i would suggest nothing is unreasonable for PCI. we did all sorts, including checking the hot water, checking all the GPO's had power, testing that the showers were…
21/07/2023
0
Hi, I am approaching end of the build. My final invoice will be given to me soon to pay. Some context before I ask my question. 1. My builder wont do the landscaping or…
3/10/2023
4
regardless, your contract stipulates a payments schedule and SOPA doesn't give provision to that scenario. Your contractual terms appear to stand. Hence get a lawyer, it…