Hi everyone, after following everyone else I have decided to create my own post with updates on our building process! Rather than bombarding everyone else.
Construction
-Slab 20th march
-Bricks arrived 14th April
-brickie booked for 16th April
-Started 28th april
-Bricks finish 30th April
-Roof frame booked 14th may
-roof frame started 18th may
-Roof frame finished 18th may
-Electrical started 2nd June
-Electrical finished 3rd June
-Roof 5th June
-Grey plaster float 9th -11th June
-Ceiling delivered 12th June
-Ceilings done 16th June
-White plaster float 22nd June -25th June (still some to be finished and fixed)
-Windows and doors 27th June
-Lockup 28th June
-Bath, laundry sink and cubords delivered 28th June
-installed 28th June