We had many problems during the entire build. Most of them are minor. I suggest you to go to the site as much as possible and pick up defects early. Though the builder says not to go to the site without someone from the them, we had no issues going on the site. Just be careful and don't get hurt!!
Selection stage was really great because we have done so much research online, magazines and visited cosham interiors few times before our colour selection. Mainitain a scrap book with your ideas and take it to your colours appointment.
I recommend you to organise for regular catch-ups with your Site Supervisor and ask him about the completed and scheduled jobs. During this meeting, go through all the defects you noticed during your sneak-ins!
Any agreements with SS should be confirmed in writing. Also I highly recommend to get an independent building inspector at Frame, Lockup (Pre Plaster) and Final inspections.
J
[IMG]http://i1344.photobucket.com/albums/p650/lcos2/IMG_1690_zps1e2dd873.jpg[/img][/img]
we added a rumpus to the back of the house
[img ][/img]
this is upstairs plan we didn't change any of the layout
[img][IMG]http://i1344.photobucket.com/albums/p650/lcos2/IMG_1353_zpsbf7c13c6.jpg[/img][/img]
downstairs we changed the front lounge to another master suite
[img][IMG]http://i1344.photobucket.com/albums/p650/lcos2/IMG_1676_zpsf04652be.jpg[/img][/img]
this is a mixture of tile and splash back colours we have picked.
we are doing our carpet and floorboards after we settle.
we are waiting on land release everything that can be done has been done. all finances and papers have been put in so once land is released we can submit to council. we are so excited and just cant wait to move into our new house.
[img]we added a rumpus to the back of the house
[img
this is upstairs plan we didn't change any of the layout
[img][IMG]http://i1344.photobucket.com/albums/p650/lcos2/IMG_1353_zpsbf7c13c6.jpg[/img][/img]
downstairs we changed the front lounge to another master suite
[img][IMG]http://i1344.photobucket.com/albums/p650/lcos2/IMG_1676_zpsf04652be.jpg[/img][/img]
this is a mixture of tile and splash back colours we have picked.
we are doing our carpet and floorboards after we settle.
we are waiting on land release everything that can be done has been done. all finances and papers have been put in so once land is released we can submit to council. we are so excited and just cant wait to move into our new house.
Related
3/05/2023
0
Building Standards; Getting It Right!
Hi All, We have a fall from road to garage front. But we cannot put a drain/grate because no discharge point put by the builder. Now they complain not enough space for…
18/08/2023
0
Hi, I have this sewer inspection point sitting in an odd spot in the rear of my yard: https://imgur.com/ghLI98q What I'd like to do is put a firepit in that corner of…
16/04/2024
1
Hi, If you give a set of criteria as to what means 'good' to you, it'll give others prompts to respond. We considered Henley early on but there were two factors that…