BLKYG looks amazing! We too have a number of things that are left to be done to get the frame to completion, however the build is still progressing without finalizing frame - roof on, rough ins done, wrapping & hebel to commence ASAP in the NY - our SS says they can still inspect the frame without slowing down the other stuff...
Interestingly, we were told that our frame was completed at the start of December and as such we were invoiced... following our Darbecca inspection we found out that the surveyor hadn’t signed off on the frame (contractually the completion of frame stage is actually subject to sign off by the surveyor). Arden have retracted the invoice and looks like frame stage won’t be officially complete till mid/late Jan. Annoyed that it feels like we’ve wasted the Darbecca inspection!!
Looking forward to updates on progress!