We bought a property in Kalamunda a year ago. Signed up with Dale Alcock back in July and are building a slightly modified Falls Creek, from their farmhouse range. We are going for a modern farmhouse look. So far, DA have been great in terms of communication, just a bit frustrating in regards to progress. I guess like everyone, we are anxious to have this house built and be living in it. This is the house we plan on living in long term.
Slab went down in mid March and apparently bricklaying is starting on Monday. Just cant wait to see this house go up. I'll post our plans and progress shots as soon as I figure out how to upload photos on this thing???
BUILD TIMELINE
Signed with DA July 2012,
Slab down 14.03.13,
Bricks started 24.04.13, Bricks finished 29.05.13,
Roof started 7.06.13, Roof finished 2.07.13
Grey float started 08.07.13, finished 10.07.13
Ceilings started and finished 12.07.13
Glazing done 2.08.13
Locked out 9.08.13
Painting started 12.08.13
Cabinets installed 13.08.13
Tiles delivered 14.08.13
Garage grano 21.08.13
Stone benchtops 23.08.13
Tiling done 11.09.13
Electrics done 11.09.13
Plumbing 13.09.13
Painting 16.09.13
Garage door 07.10.13
PCI 07.10.13
Keys 09.10.13