Browse Forums Building A New House Re: Redink Trinity, todays work 341Dec 18, 2013 5:52 pm Thanks for the info asj and cedes. We just want a nice grey/charcoal tile, prefer rectangular, but we'll see what the options/costs are. I may get a few quotes for doing it ourselves after handover, but that list seems ever growing and it feels daunting. Here's hoping they work right up until the end of the week and get more done for you:) Re: Redink Trinity, todays work 343Dec 21, 2013 7:30 pm Went up after work and the aircon is in, didn't get stolen, phew. The towel rails and toilet roll holders are done too. One bad thing though, the aircon guys put a hole in the ceiling in the kitchen!!!! Not cool. building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, todays work 345Jan 04, 2014 5:02 pm Pleasantly surprised, when I went up after finish in nights this morning the driveway had been paved and they had made a start on the alfresco! building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, todays work 346Jan 07, 2014 11:20 am Oho exciting cedes, work done when you don't know its coming is the best work. What pavers have you got? Redink Homes in Banksia Grove Handover 13/02/14 https://forum.homeone.com.au/viewtopic.php?f=31&t=65768&p=1068366#p1068366 Re: Redink Trinity, PCI booked!!! 347Jan 08, 2014 3:38 pm Woohoo got an email from CLO, PCI booked for 22nd January. Gloss being done to the doors as we speak, rest of the painting too hopefully and carpets/blinds to go in next week. The end is in sight!!! building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, PCI booked!!! 348Jan 08, 2014 3:55 pm Yay congratulations that is super exciting!! Re: Redink Trinity, PCI booked!!! 349Jan 08, 2014 4:05 pm Awesome news cedes! Nice that they got in touch to tell you as well. What do you need to do after handover before you can move in? Can't help feeling miffed about my slow progress though! Green eyed monster in me! We got our doors glossed yesterday and we don't need floors or curtains etc. You will have to let me know if your walls look like mine after they have glossed! Re: Redink Trinity, PCI booked!!! 350Jan 08, 2014 4:14 pm Hi asj, I think we should have had pci next week!!! it should be just tidy up stuff after pci, nothing big left to do, that's if in fact they get done what they say they will! Yeah I really don't understand what you are waiting for now asj, it's seems ridiculous. Have you emailed? building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, PCI booked!!! 351Jan 08, 2014 4:15 pm Oh sorry I'm wroth you now, hubby wants to get lawn down in the back garden before we move in, that's about it! The alarm, solar etc can be done after. building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, PCI booked!!! 352Jan 08, 2014 4:25 pm Ah that's good. We have to do electrical, painting, paving and flooring before we move in. Will deal with curtains and lawn later This is why I'm itching for keys. Plus we are living with my family!!! Gah! I can't believe I have to wait until end of jan given the small Amt of work left to do. Literally fly screens, door handles, garage door and service connection. Grrrrrr. Anyway I know this is how it works. I think you just get antsy when you are so close but still so far! Re: Redink Trinity, PCI booked!!! 353Jan 08, 2014 11:12 pm Great news cedes!!!! Can't wait to see pics of it all done Our RedInk Build Thread - viewtopic.php?f=31&t=64118&p=1004131#p1004131 ** Timeline Page 1 Moved In - 19.12.13 Re: Redink Trinity, PCI booked!!! 355Jan 12, 2014 11:00 am Been a busy week at the house, fly screens all in, plumbing finals done and appliances delivered and fitted. The painters are back doing the final coat and glossed the doors. And thankfully the whole in the ceiling has been fixed. Just carpets, window coverings and door handles to do next week. Almost done!!!!! building with Redink Prestart 21/3/13 Slab down 12/6/13 Brickwork started 5/8/13 Brickwork finished 26/8/13 Roof frame 6/9/13 Colorbond 26/9/13 Grey float 11/10/13 white set 17/10/13 Re: Redink Trinity, PCI booked!!! 358Jan 14, 2014 11:11 am Have they said roughly how long after PCI handover will be mate? Sounds great! Re: Redink Trinity, PCI booked!!! 360Jan 18, 2014 12:10 am So exciting!! Not long now! Cant wait to see photos! Can you give advice on how to get missing certificates needed for a form 21? Our bank requires us to provide one but we are missing 4 building certificates from our first… 3 71811 yes it does, you've just not understood it. theres a difference. 4 5322 Your house should come in "as new" condition. It should be clean, and without stains 1 4553 |