Browse Forums Building A New House Re: Building with LIH (Long Island Home) Point cook experien 3Feb 26, 2013 12:46 pm shai Hi, I am agree with you..they are very slow in building. I building in point cook with LIH. As per sales team and our agreement, construction should start in End of aug or sep 2012 but actually started in second week of oct 2012 they finish slab in Nov 2012 after month, then frame 20th dec before going on holiday. I am thinking, if they will keep delaying my home then i will sit next to their dispaly centre with banner...to tell the people they are nt worth... Be very careful when pay progress payments don't pay unless they have completed as it should be. Especially when you near lock down and fixing stage try to get a commitment when they would do handover else they will get 90% and delay it further you will be paying mortgage and a rent. Hello, Whats peoples current experience building with Carlisle, specifically in SouthEast Melbourne? We are currently building in SE Melbourne and finding that quality… 0 9170 DIY, Home Maintenance & Repair Are you going to have the frame exposed or are you cladding it with something. Usually if you are making an exposed frame you would use solid legs around 100x100 or… 3 6573 Building Standards; Getting It Right! Hi All, We have a fall from road to garage front. But we cannot put a drain/grate because no discharge point put by the builder. Now they complain not enough space for… 0 9225 |