Browse Forums Building A New House 1 Nov 16, 2012 9:40 pm Cupboards have arrived at our house now, giprock, skirtings etc all done and locked up. Our approx date of handover is Feb 18th are we on schedule for that? We are doing carpets and flooring not builder. Once your build was at the same stage how far off was your handover? Re: how long til handover are we on track? 2Nov 17, 2012 6:18 am I would say you are on schedule. It would normally take around 5-6 weeks from where you are to PCI and then another 2 weeks to attend to defects. The fact that the building industry shuts down for Christmas/January means 3 months to finish is about typical. The Harder You Try - the Luckier You Get ! Web site http://www.anewhouse.com.au Informative, Amusing, and Opinionated Blog - Over 600 posts on all aspects of building a new house. Our standard double-glazed window is tested to achieve, Rw 34, and can be glazed to suit Rw 39. The price is good too... 3 9449 Congratulations! Nice to put that to bed before christmas, now you can relax 3 7134 What? It's a lighting question, the control joint is only needed at 12m centres, a bulkhead or change of direction will suffice as a 'break' in the ceiling, just make… 8 8551 |