We haven't reached that stage yet but our slab report (via Darbecca) was 21 pages long with a fair number of defects. The SS and Darbecca seemed to work it out with the contractors eventually. Darbecca's inspector mentioned that the contractor is normally pretty good from previous experience but have a couple of new crews on jobs. They were out at our site a total of 3 times and a week and a half delayed.
Ultimately, we budgeted for this sort of stuff and extremely hppy we went with Darbecca but it's still frustrating and a reality check!
3 times? Is that Darbecca? Are you paying for a reinspection each time? Sounds like this is going to get quite costly.