Next time we build, i will make sure that the contract is changed to reflect that the date that works commence on site is stated as the contract start date (not the later of 20 days from provision of evidence of funding).
I will also remember to alter the contract to show that rain days can only be claimed prior to the roof tiles being installed and only if there has been more than 5 mm of rain.
Our builder has just claimed an extra 57.8 days (with a very lengthy and complicated calculation of how they got to this amount of days) on the practical completion date (this is also based on a 5 day work week). So they are claiming an extra 11.5 weeks onto our 25 week contract period. Add onto this the extra 4 weeks at commencement and we now have a 40.5 week build - - - wowsers!!!!! Thats almost double what they advertise.