Browse Forums Building A New House Re: builder has taken over 34 weeks 11Jul 21, 2012 5:47 pm Foremost Building Expert in Australia,assisting with building problems/disputes, building stage inspections,pre-contract review advice for peace of mind 200 blogs http://www.buildingexpert.net.au/blog Re: builder has taken over 34 weeks 13Jul 21, 2012 9:45 pm SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 Re: builder has taken over 34 weeks 14Jul 21, 2012 9:47 pm building-expert Builder is entitled to extensions of time due to variations and (reasonable) causes beyond his control. Thanks for that reminder. I was aware of extensions for rain days, but had forgotten extension due to client variations / requests along the way that might delay things a little again... SunshineT's Build: viewtopic.php?f=31&t=34585 Designs start: 4/12/09 DA: 5/7/11 Demo: 22/12/11 Slab: 24/2/12 Keys: 31/8/12 The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is. 1 8702 Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We… 0 18435 I work with owner, he/she is my man on the ground and I instruct them when to visit the site and take photos and I have other tools in the bag. 4 15244 |