Basic site costs: $6,900
Plus: Provision for rock excavation: $7,700
Plus Earthworks for 850 cut 1200 fill: $9,000
Provisional allowance for bored concrete piers under slab: $4,600
Provide concrete pump: $1,100
Material handling due to sit fall: $2,000
Provisional allowance for second water service for fire sprinklers: $2,250
Total $33,550
We have a set back of 44m, but our own earth-worker is digging all trenches for services so the additional cost in running services wouldn't be too high to the builder. This is all only for the house site too - driveway and site scrape also by our own private earth-worker.
And while we are having a laugh our council specific requirements add $41,690
BAL $6,500 provisional
Fire sprinklers $13,200
EER provisional $2,000
Rainwater tank (potable water source) $12,250 plus $590 plus $3,105 for concrete pad and retaining wall
Coloubond roof $4,595
Sewerage pod $5,500 plus $450 for power
OMG!!!!!! where are you building????
You in a BAL FZ?????