Browse Forums Building A New House 1 Feb 28, 2008 11:00 pm Re: Building stages 7Feb 29, 2008 5:46 am Hi DeeElle, I asked the same question to my builder last week
I really thought our roof would be next after completion of frame, instead some of the windows were installed. This is the order for a second story( my build at least) Frame completed Windows Bottom brick work to about head high Scaffolding Roof can now commence with rest of brick work etc Plumber does a rough in Lock up Bill My builder explained to us that it was for the safety of the workers that the roof and upper story cannot be worked on until the scaffolding is up. Any way, that is the order of mine, but I have noticed that other builds are different Mrs B go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110570 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11035 |