Our first time build is the SOHO 2400
so far the admin stage has been 4 months, burbank has everything running smoothly and hopefully we will start building in 4 weeks! I have everything crossed xxxxxxx
we have changed the plans to include a walk in pantry,and put in a roller door and window at the back of the garage.
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
This is our progress so far-
deposit on land May 2011
signed with DFH May 2011
cancelled DFH August 2011
signed with burbank August 2011
job accepted 06/10/2011
1st working drawings 17/01/2012
color appointment 15/02/2012
2nd working drawings 29/02/2012
developer approval 06/03/2012
land available 16/03/2012
soil test complete 23/03/2012
working drawings finalised 03/04/2012
land finance aproved 12/04/2012
enginiering complete18/04/2012
land settlement 26/04/2012
contracts signed04/05/2012
building permit 10/05/2012
finance approved 18/05/2012
earthworks 31/05/2012
setout01/06/2012
slab09/06/2012
frame15/06/2012
roof 27/06/2012
electrical roughin 03/07/2012
plaster 17/01/2012
lockup24/07/2012
painters25/07/2012
fix out27/07/2012
electrical fit out07/08/2012
carpet10/08/2012
plumbing fixout24/08/2012
PCI 24/09/2012
settlement 08/10/2012