After 6 months of admin stuff like soil test and site costs which took 3 months the plans took 10 weeks
A problem with the bank as there was a stuff up by the agents when we purchased the land a name was spell wrong so we had to pay 150 to have it fixed as the bank would not lend the money
Yesterday we approve the plans and the contract should be ready to sign next week
and the week after that into council for around 6 to 8 weeks
and then 18 weeks to build
all up will be around a year
So I am getting excited now but still a long away to go
I after to said I am a little bit scare about the build process its the un certained on it now doing until they start diging if their will be any extra charge rock etc.