I had a thread running in here earlier in the year, but had it taken down due to privacy issues. I know a few people in here were following it though, so I thought i'd give a bit of an update for y'all

We had our final inspection on Wednesday, and we are having handover next Thursday! YAY! We're quite pleased about this as you'd expect. Given our initial contract said we'd be handing over in December, this is a big step up

PCI went smoothly. We only had 8 defects that needed fixing and 5 of those were paint defects. Beyond that they just have to replace the track on the sliding door as it has a dint, re-seal the join between tiles and front door and replace a kitchen cupboard that had a chip in it. That's it really.
So unless the bank drops the ball, we'll be in next week!