Our kitchen was installed yesterday, tiles have been delivered, walls are all up but still some cornice to go.
Timeline to date is site start 4/05/11
Slab 20/05/11
Frame 30/05/11
Bricks 27/07/11
Bit slow but we've had some hold ups with weather and bricks out of stock.
Just wondering how long it normally takes from this point untill handover?