what do you mean exactly?
He said that no job is quoted at sales with the required slab, which is always over spec... It's where their margins come from...
And it's not unique to PD
Yes correct -they provide slab requirements and cost after the sales quote at contract stage, once they have done soil tests etc...like most builders.
However changes to our slab were made (some reinforement items removed) after we signed our contract, without any notification or credit offerred to us- until we raised the issue....