Hi All,
Interest in peoples experience with times from plastering completion to handover?
Cheers
Browse Forums Building A New House Re: Timeframes 2Jul 17, 2011 11:57 pm Our walls were finished on the 27/8/10, the cornices and skirting boards were finished on 2/9/10 and the doors were hung / pantry shelves installed etc on 6/9/10 and we had handover on 18/10/10, so exactly 6 weeks from the day that all the gyprock / doors etc were finished to the day we got the keys. Good luck! Nic. Built the Coral Homes Hamilton 252 - moved in 20/10/2010 and loving it!! https://forum.homeone.com.au/viewtopic.php?t=27215 |