Aveling Homes - Southern River WA Perth few questions!!!!!!
Page 1 of 1
Since Aveling Homes had everything ready (with 1 year to prepare) the plans went straight to council Early Mid June. Now I have a question!
Do they site scrape the land after or before building licence approval.
You see July 7th our files got trasnfered to construction side in Aveling and today we got a call from our new (loookerer afterer person thingy) saying they will be starting construction this week. I don't even know her name, so not sure if it's even a supervisor!
Today I was standing at the block when I got that phone call, I didnt tell her haha but I was - and the site had been scrapped already. No portallo, no pipes, no machinery. Does this mean the building is already approved, and so that lady is my supervisor?? I had thought since we have a tap at the block we had building approval, which turned out wrong, so am i right this time?
In terms of Aveling for those reading wanting feedback so far.
They're customer service is outstanding. So far. I've always been a little reluctant with them but they always seem to impress, maybe because I expect so little? I had one problem which resulted in my house flipped the other way which to this day, I still think I'm right but anywho, they are great so far but they have had a lot of time to think hahaha!
Will keep questions coming along with photos.
Also what's some main big problems you expect to see when building a house?
And if they take longer then they're (so and so) days to build the house, what happens? What can I do? I read somewhere that the contract has to have a $$ per day on there, otherwise you cant do anything but wait? Is this true? I heard Aveling build fast and good, and so fingers crossed they continue to preform well.
I think the standard hia contract allows close to a year before they have to pay
Liquidated damages, so it's unlikely they'll take that long.
Slabs around me have been done before portaloos.
I think that's all you asked.
Good luck, hopefully well both be building soon.
They were our 2nd choice but we decided on redink, I believe the quality of avelings Finnish to be 2nd to none!!! (I'm pretty sure they are part of zorzi group and their homes are majestic)
And yes, photos are a must!!!!
Hey Leona I read your house thread. your unique house design is so good! We were going to go with red ink homes too! Not quite sure why we didn't to be honest, I think we were just on Avelings spell haha!
yes!
im a pic piggy and im watching this space
i am sure you have had your colourbond/roof tile moment and i wanna seeeeeeeeee
xx Leona
I'm going to build with Avelings too and I'm a bit worried about the costs for additions from the inclusions, so if anyone can brief me on what additionals you've included at prestart and the price that would be great!!!
Related
22/05/2023
7
Personally, considering your layout (study/work desks in bedrooms), I don't think you have any other option but to leave NW windows and make them as big as possible e.g.…
23/05/2023
1
We had this happen to us last year and got charged a variation. Try and give away as much as you can that is usable to charity otherwise if you are in Sydney I have a…
7/07/2023
1
Not sure what council area you are in. Some LGA's allow zero lot retaining walls. This usually occurs in greenfield developments but not often in established areas. You…