Browse Forums Building A New House 1 Jun 21, 2011 1:46 pm I know generally there is about 5 days from slab to framework beginning for project homes but what I'm not sure of is how long is there usually between the concrete piering going in to when the slab gets laid? Time from piering to slab 2Jun 21, 2011 3:00 pm Our piers were laid on a Tuesday then the formwork is done and then slab laid which was poured the following Tuesday but we did have some rain in between which delayed a day..... Good luck Land Settlement - 1/10/10 Slab 23/3 Frame 14/04 Roof Tiling 29/4 Bricks 5/5 Electrical Rough In 27/5 Gyprocking 23/6 Kitchen install 29/6 Tiles 14/7 Paint 4/8 Plumbing 27/7 Were in 1/9 9 24751 1 13116 Can anyone give me any onfo on New Homes WA? Good or bad, hopefully good just need to know if my choice was good or not? Thanks ❤️ 0 8933 |