Hi Guys!
Needing some urgent advice. Basically building with F*wler Homes and are passed council and have had the peg out completed. Expecting the slab to go down this week and we have just recieved an email off the builders letting us know that the concreters have been out to inspect and prepare for works to commence with the slab. We have now been told there is up to 50 loads of fill to be removed, They can happily do this for us at the cost of $442 per load inc Gst, alternatively if we know of somebody else that can remove the fill from site next week thats fine too.
So basically the cost to remove this fill is $22.000.
Suggestions, Thoughts, ideas? Before I crawl into the fetal position and cry?