Building the Southport from HGWA at Madora Bay
Our second build, but still frightening.
5-10-15 Building Contract signed
3-12-15. Pre-start
5-2-16 Finance approved
8-2-16 Finance Signed
22-2-16 Pre-start signed
16-3-16 Final plans signed
16-3-16 in for scheduling
16-3-16 Tap in
23-3-16 Approved Building Permit Received
7-4-16 PowerBox installed
13-4-16 Pad Prepped
21-4-16 SLAB POURED
29-4-16 Soakwells installed
3-5-16 Bricks arrived
9-5-16 Brickwork started
20-5-16 Brickwork finished
25-5-16 Roof Framework started
8-6-16 Colourbond started
14-6-16 Colourbond finished
14-6-16 Grey Float started
23-6-16 White Set and Cornice Started
18-7-16 Glass fitted
19-7-16 Front door fitted/ lock up
21-7-16 Cabinets started
25-7-16 Fixing Carpenter
25-7-16 Tiler started prep
27-7-16 Tiles delivered
27-7-16 Shower membrane added
27-7-16 Stone bench top installed
28-7-16 Garage floor poured
1-8-16 Tile meeting
2-8-16 Splashbacks measured
3-8-16 Tiling started
12-8-16 Freestanding bath and toilets delivered
16-8-16 Oven and HWS delivered
16-8-16 Tiling finished
17-8-16 Electrical started
17-8-16 Plumber installed toilets, tapware.
17-8-16 HWS installed
18-8-16 Splashbacks installed
19-8-16 insulation delivered
19-8-16 cornices finished in wet areas
22-8-16 Insulation installed
22-8-16 Prep for paint doors and frames
23-8-16 Mirrors, Robe Doors installed
23-8-16 Texture Render started
23-8-16 Freestanding bath installed
24-8-16 Air-Con installed
26-8-16 Shower Screens started
26-8-16 plaster holes fixed
30-8-16 Texture Render completed
30-8-16 Shower screens and mirrors completed
31-8-16 Garage door installed
31-8-16 Front door stained.
1-9-16 Internal clean
2-9-16 Site clean
12-9-16 Carpets installed
12-9-16 Flyscreens installed
14-9-16 Paint touch up
15-9-16 Site clean
19-9-16 Deadbolt and towel rails
21-9-16 Site toilet gone
22-9-16 Driveway/path prep. Mesh delivered
23-9-16 Driveway/path poured
24-9-16 Driveway/path washed
3-10-16 PCI completed
3-10-16 feature pier capping complete
11-10-16 Driveway sealed
18-10-16 Final internal clean
20-10-16 PowerBox removed
2-11-16 2nd PCI
2-11-16 WE HAVE KEYS
3-11-16 Letterbox installed
3-11-16 prep for painting
4-11-16 Undercoat started
7-11-16 Undercoat finished
7-11-16 boundary wall cored
9-11-16 Colour started
11-11-16 Fencing completed
18-11-16 Painting completed