Browse Forums Building A New House 1 Feb 10, 2011 5:31 pm Hi We have a build underway with Beechwood. There are two weeks away from being out of contract after adding extra days for xmas, rain and hloidays. There was plenty in the contract about our responsibility but nothing about theres. Any ideas? Louise Re: What is our rights when build goes over contract? 2Feb 10, 2011 5:33 pm Most contracts state that the builder will pay you xxx dollars per week if the contract goes over the completion date. Do you not have anything like this in your contract? Is it a standard HIA contract or other? The only thing to add to these comments is that where possible it's always good to try and work with people than just say "no" because you can. Having someone… 4 17107 Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 17511 You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16542 |