Was just wondering how many of you at the end of your build your rock provision covered the cost and therefore received a credit for the difference?
My provision was around $7k (35 cubic metres), but I have seen the rock removed and have photographed the rock removed and it looks only 4 cubic metres. Therefore I expect a $6k refund.
My solicitor has told me that as stated in the HIA contract the builder has to provide invoices which they received for rock removal as evidence of their charging onto myself.
Did you all receive this evidence or just accept the rock removal costs? Is it likely for a large company like H3nley to 'boost' what they charge clients for rock removal ?
If I receive anything less than an unsustantiated $6k, I will have to pass it onto my property solicitor.
Cheers