Browse Forums Building A New House Re: Burbank Evolution 2300 2Dec 13, 2010 10:29 pm Hi there, I'm also building evolution 2300. I haven't started to build yet due to land being delayed. And I think they put 260 days to cover there arses. Where are you building btw? I'm in Somerfield Estate in keysborough. DAP 7/3/2011 Site start letter 13/4 Earthworks 1/5 Set out 16/5 Storm water and sewer 16/5 Frames 30/5 Roof Tiles 7/5 Lock Up 23/6 Fix Out 30/6 Electrical 20/7 Plumbing 25/7 PCI 19/8 Re: Burbank Evolution 2300 3Dec 13, 2010 10:50 pm PCJ, check out this thread: viewtopic.php?f=31&t=12475 From what I've read most Burbank builds seem to take around 4 months from when the slab is laid, allow an extra month if your build includes the Christmas shutdown. Building the Ascent 3000 with Burbank http://www.burbank.com.au/HouseDetails.aspx?houseId=82 viewtopic.php?f=31&t=39638 Re: Burbank Evolution 2300 4Dec 15, 2010 9:41 pm hi ginz88.... I have not started either but have signed contract last week and most probably start will be mid/late Jan. and i am building in Cranbourne north. Can i ask what facade you are going with, i am going with the standard colorado. Re: Burbank Evolution 2300 6Dec 15, 2010 10:16 pm I am also going with the Colorado (rendered) facade. Funny thing is, when I did the colour selection it ended up being very similar to the picture on the Burbank website. More info on my build, I spent about $40k+ on upgrades. DAP 7/3/2011 Site start letter 13/4 Earthworks 1/5 Set out 16/5 Storm water and sewer 16/5 Frames 30/5 Roof Tiles 7/5 Lock Up 23/6 Fix Out 30/6 Electrical 20/7 Plumbing 25/7 PCI 19/8 Re: Burbank Evolution 2300 7Dec 16, 2010 6:26 am hi ginz88 ... Mine is an investment property and I am not spending much at all on upgrades . How was the colour selection.... Did they have much of a choice in the builders range ? I haven't got an appointment as yet but I hear it is like a full day session. Re: Burbank Evolution 2300 8Dec 16, 2010 10:27 am It took me 7 hours to do my colours, my first build so yeh. It shouldn't take that long doe yours if it's an investment property but good luck anyways. DAP 7/3/2011 Site start letter 13/4 Earthworks 1/5 Set out 16/5 Storm water and sewer 16/5 Frames 30/5 Roof Tiles 7/5 Lock Up 23/6 Fix Out 30/6 Electrical 20/7 Plumbing 25/7 PCI 19/8 Hi All, Recently we have signed a contract with Burbank and we are not aware that they have just DORSET, SURREY, HAMPSHIRE, KENT, PILBARA and REDGUM bricks from PGH are… 0 3108 |