The progress so far:-
Land Available 19/07/2010
31/05/2010
Building Contract Signed 09/06/2010
19/05/2010
Colour Selection 28/06/2010
Working Drawings 11/10/2010
Developer Approval 03/11/2010
Building Permit 09/11/2010
Chase up Signed Final Dwgs 19/11/2010
Finance Approval 03/11/2010
Land Settlement 06/07/2010
Site Start Letter Sent 23/11/2010
Earthworks 03/12/2010
Set Out 02/12/2010
Stormwater & Sewer 02/12/2010
Progress Claim - Base 13/12/2010
Framer 15/12/2010
Progress Claim - Frame 16/12/2010
Fascia/Gutter 22/12/2010
Roof Cover 14/01/2011
Electrical Roughin 17/01/2011
Progress Claim - Lockup 18/01/2011
Plaster - 07/02/2011
Progress claim Fix Out - 10/02/2011
Electrical fit off - 10/03/11
Plumbing fit off - 15/03/11
SETTLEMENT - 16/05/2011