Hi All
I Have a question regarding handover
we had our pci tonight and besides the little things like touch up's here and there and caulking the wet area's
the 2 main issues which i have brought up are the roof tiles which are broken on the corners and the amount of different colour roof tiles
and evap cooler which ha a dent in the pipe that comes through the roof which stands out
he got a certificate of CVO today apparently and wants to do handover thursday
what do i do he says he has booked the roof tiler to come do a maintance call and the evap cooling guy as well
I said i wont hand over the final payment until these items are done his answer is they will be noted on the paperwork as incompleted and done in the next few days otherwise he will let the house sit as is until the day the contract is due which is end of Jan . My question is can he afford to leave it sit there with all the vandals in the area or do i play his bluff and say let it sit until the contract date or play along with him and take his word for it