Now that we have our Building Permit I figure it is time to start our own thread for our build as the start date draws ever nearer.
Building the Ascent 3000 with Burbank in Aitken Park, Craigieburn.
http://www.burbank.com.au/HouseDetails.aspx?houseId=82
Our floor plan with some minor amendments:
Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅
8/4/10 - Job acceptance
13/5/10 - Contract signed
21/6/10 - Land settled
28/6/10 - Colour selection
16/7/10 - Working plans
30/7/10 - Engineering
11/10/10 - Building permit
18/10/10 - Final construction plans
20/10/10 - Site start letter
4/11/10? - Site scrape
29/11/10 - Slabbed
6/12/10 - Framed
10/12/10 - Fascia & guttering
27/1/11 - Lockup
28/1/11 - Plaster
4/2/11 - Fixout
21/2/11 - Painting
21/2/11 - Plumbing Fixtures
7/3/11 - Electrical Fitoff
15/3/11 - Plumbing Fitoff
15/3/11 - Tiling
18/3/11 - Driveway
21/3/11 - Carpet
14/4/11 - PCI
28/4/11 - Final Inspection
2/5/11 - Settlement/Handover