Wow good progress. As the tiles are delivered, they will start the work on tiling soon very good progress
Can't see any reason why not. It looks like we are on track with other Burbank builds, ie painting completed within 2 to 3 weeks of completion of Fixout Stage.
Typical progress for Burbank builds seems to be 2 to 3 weeks from Fixout to painting, 1 week for tiling then another 1 to 2 weeks for electrical/plumbing fitoff and carpet. After all that is done PCI is about 3 to 4 weeks later to allow for all the incidentals, ie driveway, blinds, etc plus Quality Assurance and I'm guessing the Certificate of Occupancy is applied for before or around PCI.