Browse Forums Building A New House Re: When do you pay for Post Contract Variations? 7Oct 01, 2010 1:25 am viewtopic.php?f=31&t=37229 - our Iris 4! Re: When do you pay for Post Contract Variations? 20Mar 12, 2020 12:45 am I'm not sure what the HIA contract says in other state but in WA the variation is due at the next progress payment claim after the work is completed. We (I work for a builder) will alter the progress payment claim schedule if Variations go over $20k, makes it fairer for both parties, any credit variation are adjusted at the final progress payment, that's how it is written in the contract. It seems very clear to me that your contract states that a security account does NOT need to be established so the answer to the builder is NO. If in doubt find a contract… 1 8512 So AFAIk the outcomes of the BAL ratings form part of a clause that allows them to pass these costs on to you. However the more relevant detail is how did it go from 19… 1 9170 The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is. 1 8711 |