I can't find it in my paperwork.....maybe I've missed the clause
, but

...........do we get a 12 month maintenance inspection ?

edit : typos
bump...........anyone ??
I'm not sure, I thought it was just 3 months
That's what I'm afraid of FH
nothing in my paperwork re: 12 month.

Do you have a problem with something?
Hi Guys,

Per clause 29 in the contract "Defects Liability Period" is a period of 13 weeks commencing on & inc the "date of practical completion"
No. No probs KID ( just settling issues eg cracks, etc) just wondered whether we got the 12 months as a VIC builder.......forgot the name