Browse Forums Building A New House 1 Jul 29, 2010 9:17 pm Generally speaking, how long does it normally take from roof being covered to lockup stage, and then from lockup stage to PCI ? Please let us know of what your timeframes were. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 Re: Roof Covered to Lockup to PCI 3Jul 30, 2010 8:06 pm grom40 My timeline was roof tiles 26/5, lock up 25/6. I should be at PCI within a fortnight (mid August). Will vary depending on the size/ complexity of your house (& how efficient the builder is ) Thanks for that grom40. Atleast i get a rough estimate, hopefully more people will reply and we can get an average. I hope your PCI goes really well. You must be really excited, not that all the wait is coming to an end. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 Re: Roof Covered to Lockup to PCI 5Jul 31, 2010 2:20 am Just an guesstimate, but roof tiles until lock up was around two to three weeks from what I remember. We've been locked up now for two and a half months, perhaps even longer and PCI is still at least a few more weeks from now. Our build from site scrap until now has taken seven months so far Dear J.K. Rowling, Your books are entirely unrealistic. I mean, a ginger kid with two friends? Sincerely, Anonymous Re: Roof Covered to Lockup to PCI 6Jul 31, 2010 4:29 pm The Little Misses Just an guesstimate, but roof tiles until lock up was around two to three weeks from what I remember. We've been locked up now for two and a half months, perhaps even longer and PCI is still at least a few more weeks from now. Our build from site scrap until now has taken seven months so far I think waiting after lockup will be the hard part, as you cannot see everything and i think the progress may not be as visual as it used to be until lockup. Hopefully everything works out well for you and you get your PCI very soon. Good Luck. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 We hired Darbecca to do every stage inspection, and I strongly recommend them to anyone that asks me. They were amazing. Thorough reports with photos at every stage,… 6 7127 i would not be signing anything on the day read your contract about when builder submits final invoice generally, have to meet builder within 7 days of receiving final… 1 4735 2 9446 |