CC101
sand was compacted and slab poured on 19 oct. Then on 21 oct morning they digged along the sides of slab to connect plumbing pipes. Sides of slab have not been compacted yet. Would that not disturb setting of slab? The guys who were doing digging / plumbing work on 21 oct said they are suppose to do this work monday on 24 oct but doing work ahead. my concern is if it disturbs slab curring / setting etc if area is digged on sides of slab (so soon after pouring slab) and is not compacted yet
I doubt that them doing this plumbing would cause any structual issues. If they did it the same day as the pour than maybe but a couple days after not likely. they wouldnt actually dig under the fotting to unsettle it. If you do have any concerens bring it up with the builder. If it wasnt ok to do then i guess they wouldnt do it.