Browse Forums Building A New House 1 Jul 15, 2010 11:50 am Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 2Jul 15, 2010 12:04 pm Land Settled: 29 March 2010 Pre contract & Deposit paid - 17 May 2010 Pre Start & Contracts Signed - 16 June 2010 Council Approval Received - 30 June 2010 Slab Down 30 July 2010 Plate High - Late August Lock Up - TBA Re: Copy of Bank Docs to Builder 3Jul 15, 2010 12:18 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Copy of Bank Docs to Builder 4Jul 15, 2010 12:30 pm Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 6Jul 15, 2010 12:49 pm Site Start: 10th September, 2010 PCI : Friday 27th January, 2011. Handover: 3rd February, 2011 Build Thread: viewtopic.php?f=31&t=37677 Re: Copy of Bank Docs to Builder 9Jul 16, 2010 10:51 am Land Settled: 29 March 2010 Pre contract & Deposit paid - 17 May 2010 Pre Start & Contracts Signed - 16 June 2010 Council Approval Received - 30 June 2010 Slab Down 30 July 2010 Plate High - Late August Lock Up - TBA Re: Copy of Bank Docs to Builder 13Jul 17, 2010 5:02 pm ring09 No fixed site costs, we were only just given a final price for site costs after final site/soil etc, with another provision of 6k for rock removal etc, how much do you want to bet that they will use all of this 6k. i understand the cynicism as we had similar provisions in our contract. though a few weeks after slab was down they had the final figures and did the balancing adjustment, there was a substantial crediting back of the provisions, except rock at that stage, as there were still a few things to do Re: Copy of Bank Docs to Builder 14Jul 17, 2010 5:05 pm mav999 ring09 No fixed site costs, we were only just given a final price for site costs after final site/soil etc, with another provision of 6k for rock removal etc, how much do you want to bet that they will use all of this 6k. i understand the cynicism as we had similar provisions in our contract. though a few weeks after slab was down they had the final figures and did the balancing adjustment, there was a substantial crediting back of the provisions, except rock at that stage, as there were still a few things to do and i forgot to add, when they did hit rock i got a call and was given the option to go out there, the drainers gave me the dimensions and copy of the plans with rock, shale and measurements all marked, from the provision per cubic metre which they set out in the contract, the rock expense was pretty much spot on Re: Copy of Bank Docs to Builder 15Jul 17, 2010 5:46 pm We are with one of the big four banks, didn't go through a broker, and also needed to provide our signed documents to our builder. We also needed a letter from our conveyer that proved settlement on our land, before they would step foot onsite. We are building with a small family builder. Just protecting themselves really. Dear J.K. Rowling, Your books are entirely unrealistic. I mean, a ginger kid with two friends? Sincerely, Anonymous How much are you ahead in payments compared to where the build is at? Have you fully drawn down the loan? 5 11926 Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 20417 |