Browse Forums Building A New House 1 Jun 18, 2010 10:17 am Well its been a long time coming but the slab was finally poured yesterday. So far so good we were told around the 15th of June so they came in on time for this one. 17 JUNE SLAB DOWN 23 AUGUST BRICK WORK COMPLETE 15 SEPTEMBER ROOF COMPLETE 25 SEPTEMBER FIRST FLOAT COMPLETE 5 NOVEMBER LOCK UP 12 NOVEMBER GRANO POURED 27 NOVEMBER TILING COMPLETE 8 DECEMBER DEFECTS FIX AND FINAL CLEAN STARTED https://forum.homeone.com.au/viewtopic.php?f=31&t=34992 Re: SWITCH HOMES TEN70(MODIFIED) 2Jun 18, 2010 3:16 pm Right, now it's time for pics and plans feggle! Don't leave us hanging! Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Re: SWITCH HOMES TEN70(MODIFIED) 3Jul 02, 2010 6:15 pm westy Right, now it's time for pics and plans feggle! Don't leave us hanging! Re: SWITCH HOMES TEN70(MODIFIED) 4Jul 05, 2010 10:36 am Hi all, my apologies for jumping in, we are signing with Switch and are feeling the pain with the paperwork delays. i have been following what forums i can find on Switch and everyone's experiences, but nothing has been mentioned regarding the switch packages IE carpet, art etc also did you all have the decorator consult before pre-start. i have a million questions.... we are hoping to sign the contract within 2 weeks, no one likes to think they have it wrong or could have/should have.... cheers molly2/switch SOR Re: SWITCH HOMES TEN70(MODIFIED) 5Jul 11, 2010 3:41 pm Hi molly2 How's the paperwork going? Ours took about 6 months. Which plan are you building? We have asked numerous times for info on the Sw1tch Select packages, however the only thing we were told was that they have arrangements with certain suppliers and we could have the contact details of these suppliers if we wanted. I got the impression that we would have to contact them and arrange quotes etc ourselves though. We still haven't received the contact info despite asking for it a couple of times. Re the interior design services, there are 3 options to choose from - Tile & Laminate, Tapware & Sanitary, and Colour Board. These are all $300 (as of January). They say they can also customise an interior design service. We didn't bother with these. Good luck, let us know how you go. Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Re: SWITCH HOMES TEN70(MODIFIED) 6Jul 11, 2010 11:42 pm Hi We are building the switch ten70, although very modified. We are yet to finalise our documentation, prestart was seven weeks ago. We have going at this now since the start of March!!! It seems very messy the convoluted and drawn drafting process. I wish we could just sit down with the drafty for a half a day and we could get it all sorted. We asked about the "design service" and even went to book a session, but the lady doing prestart told us not to worry about it and she was a qualified interior decorator and that she can help if we needed any help. The consultants at the tile places will also assist with selections, as will the consultants at the laminex shop. We went to the display home in baldivis today and the SR told us that the build time at the moment is about 5-6 months. Re: SWITCH HOMES TEN70(MODIFIED) 7Jul 12, 2010 9:57 am Thank you both for your reply, we have only been going through this for 5-6 weeks now, but it has been completely unnecessary due to the incompetence of the SP, we knew what we wanted and made only minor changes (apart from the elevation) with a lot of upgrades. it is frustrating as Switch are supposed to be the BMW of builders and profess to be equal to W&B but the service is on par with Content! i will be contacting the office today and will no long deal with the SP, lets see if they can redeem themselves, as we are yet to understand who in the process will be actually to blame. in regard to the design service all the Switch advertising states free decor service included, but not until we got the pre-start pack (which is extremely well put together) the fee of $300! is mentioned, i feel confident we don't need it but it would have been good to confirm the choices with someone more qualified in colour! cheers Re: SWITCH HOMES TEN70(MODIFIED) 8Jul 13, 2010 8:34 pm Sorry for the delay - brick work started today - after a big week of horrible weather - pics to come Here is the plan - i got carried away cropping it - it's 265m2 living + alfresco etc omg can some one help me!!!! how on earth do you attach plans and pics ??? grrr Follow Feggle viewtopic.php?f=31&t=34992 Follow lilfeggle viewtopic.php?f=31&t=37149 Asbestosis Sux! Don't breath in Asbestos Re: SWITCH HOMES TEN70(MODIFIED) 9Jul 13, 2010 9:26 pm Hi lilfeggle, that's good news that they have started! Be good to see some pics. See this thread (the reply by wizard) for instructions on how to post them in here: http://forum.homeone.com.au/viewtopic.php?f=13&t=28598&start=0 Let us know if you have any problems. Re: SWITCH HOMES TEN70(MODIFIED) 10Jul 15, 2010 9:13 am The brickies are up to day 3 today. So far the have done heaps, all the way from the kitchen/alfresco wall round the back and down to the front bedrooms!! At this rate they should be finished in about 2-3 weeks. http://i811.photobucket.com/albums/zz34/feggle/finalplans6.jpg 17 JUNE SLAB DOWN 23 AUGUST BRICK WORK COMPLETE 15 SEPTEMBER ROOF COMPLETE 25 SEPTEMBER FIRST FLOAT COMPLETE 5 NOVEMBER LOCK UP 12 NOVEMBER GRANO POURED 27 NOVEMBER TILING COMPLETE 8 DECEMBER DEFECTS FIX AND FINAL CLEAN STARTED https://forum.homeone.com.au/viewtopic.php?f=31&t=34992 Re: SWITCH HOMES TEN70(MODIFIED) 11Jul 15, 2010 9:17 am Bricks arriving about 3 weeks ago photo http://i811.photobucket.com/albums/zz34 ... -07-10.jpg[/IMG] 17 JUNE SLAB DOWN 23 AUGUST BRICK WORK COMPLETE 15 SEPTEMBER ROOF COMPLETE 25 SEPTEMBER FIRST FLOAT COMPLETE 5 NOVEMBER LOCK UP 12 NOVEMBER GRANO POURED 27 NOVEMBER TILING COMPLETE 8 DECEMBER DEFECTS FIX AND FINAL CLEAN STARTED https://forum.homeone.com.au/viewtopic.php?f=31&t=34992 Re: SWITCH HOMES TEN70(MODIFIED) 12Jul 15, 2010 12:04 pm Hi feggle thanks for the pics, looks good! Have they started bricking yet? BTW, to get your pics to show up in your post, when you are replying select the whole 'http://...' text and then click on the "Img" button just above the post box. It will put the image tags around the link which will insert the pic into your post. You can click on "Show Preview" to check that it has worked. Re: SWITCH HOMES TEN70(MODIFIED) 13Jul 15, 2010 8:46 pm Hi Westy It's day 3 of bricking and they've done a lot ... feggle has posted the floor plans too, now that we know what we are doing, i've a load of pics on my camera i can download... how's your build coming along? Follow Feggle viewtopic.php?f=31&t=34992 Follow lilfeggle viewtopic.php?f=31&t=37149 Asbestosis Sux! Don't breath in Asbestos Re: SWITCH HOMES TEN70(MODIFIED) 14Jul 15, 2010 8:50 pm abbeybox Hi Abbeybox Post your floor plans - we're also building the ten70 very modified...see "feggle" he's put our plans up....the brickies are on day 3 of laying..although it's taken alot of time to get to this stage, the building seems to be going smoothly We are building the switch ten70, although very modified. We are yet to finalise our documentation, prestart was seven weeks ago. We have going at this now since the start of March!!! It seems very messy the convoluted and drawn drafting process. I wish we could just sit down with the drafty for a half a day and we could get it all sorted. We asked about the "design service" and even went to book a session, but the lady doing prestart told us not to worry about it and she was a qualified interior decorator and that she can help if we needed any help. The consultants at the tile places will also assist with selections, as will the consultants at the laminex shop. We went to the display home in baldivis today and the SR told us that the build time at the moment is about 5-6 months. Follow Feggle viewtopic.php?f=31&t=34992 Follow lilfeggle viewtopic.php?f=31&t=37149 Asbestosis Sux! Don't breath in Asbestos Re: SWITCH HOMES TEN70(MODIFIED) 16Jul 22, 2010 10:10 pm insert 17 JUNE SLAB DOWN 23 AUGUST BRICK WORK COMPLETE 15 SEPTEMBER ROOF COMPLETE 25 SEPTEMBER FIRST FLOAT COMPLETE 5 NOVEMBER LOCK UP 12 NOVEMBER GRANO POURED 27 NOVEMBER TILING COMPLETE 8 DECEMBER DEFECTS FIX AND FINAL CLEAN STARTED https://forum.homeone.com.au/viewtopic.php?f=31&t=34992 Re: SWITCH HOMES TEN70(MODIFIED) 17Jul 22, 2010 10:21 pm insert 17 JUNE SLAB DOWN 23 AUGUST BRICK WORK COMPLETE 15 SEPTEMBER ROOF COMPLETE 25 SEPTEMBER FIRST FLOAT COMPLETE 5 NOVEMBER LOCK UP 12 NOVEMBER GRANO POURED 27 NOVEMBER TILING COMPLETE 8 DECEMBER DEFECTS FIX AND FINAL CLEAN STARTED https://forum.homeone.com.au/viewtopic.php?f=31&t=34992 Re: SWITCH HOMES TEN70(MODIFIED) 18Jul 22, 2010 10:24 pm amazing .... i'm so excited Follow Feggle viewtopic.php?f=31&t=34992 Follow lilfeggle viewtopic.php?f=31&t=37149 Asbestosis Sux! Don't breath in Asbestos Re: SWITCH HOMES TEN70(MODIFIED) 19Jul 22, 2010 11:27 pm Well done feggles! Love the pics and great to see another 'Sw1tcher' at it. I thought our 'scullery' was quite big, but I've just noticed yours is huge! With a sink and all! Makes ours just look like a fridge recess.... You are certainly not going to be short of storage in that house! Built with Sw1tch H0mes >Build thread< House status 15/12: Gates and A/C finally installed! Sep 09 Bought block, Dec 09 Engaged builder, Jul '11 Moved in Any electricians here please help. 1) Will the Fan need separate switch to ON/OFF/Speed eventhough it comes with Remote 2) how about… 0 1228 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74717 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105617 |