Browse Forums Building A New House 1 Jun 15, 2010 9:17 am Refer to your UIN number in bold writing at the start of the letter. State that you signed the contract knowing that it was reasonably foreseeable that you would have slab laid by 6 month deadline. You will need to attach proof to your letter, do these as dot points and refer to them as appendice 1,2,3 etc. For example appendices should be: Extract for land contract showing when settlement will be: Extract from building contract showing date signed and signatures. Now, I also included 2 more appendices including. An email from the developer saying titles were due in November And another letter which also helped me. From the above I have shown that I was able to prove that I reasonably expected to start within 6 months. Each of you will have differing circumstances but my advice will be: Email the developer/ real estate agent and ask when titles will be released. If there is a problem, ask what it is. EG I know one estate has been delayed by like 9 months due to the amount of rock, well get that in an email from the developer. Dont say that you will be using it for SRO purposes, just send them a friendly email. Hope this helps some people out there. The HIA contract, in the term & conditions section states that "Commencment" is deemed when the drainage is started or the piers are dug or the slab is formed up (incase… 2 6182 Hi all Am new to this forum. I want to get some ideas/info about how to manage an 80 year old factory restoration to convert to a residence. The factory floor is concrete… 0 6345 Have look at your house plans and you will probably find that brick articulation joint has been missed. Maximum allowable spacing is 6M or 5.5M for a wall with window… 17 20606 |