Browse Forums Building A New House Re: How to get payment of 'Late Completion Damages' 7Oct 02, 2007 11:43 am Have you calculated how many raining days in that past X months during your constructions? Also, depending on the contracts, like in ours the builder added a clause saying for every raining day it requires another day for it to dry.
So if you minus the number of raining days, may be it hasn't reach the specified construction periods yet?? Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines… 7 10743 It worked for me in getting all non notified rain days removed from the builders claim, although the LDs was only $50/day 7 5940 |