Double brick home, when do the sparkies and plumbers come?
Page 1 of 1
Slab
Brick Work (Internal and External Walls)
----- Plate High ----
Roof (Trusses and Formwork)
Electical
Pluming
Tiles/Sheeting
Render
Ceiling
Plaster
----- Lockup ------
<Rest of the Internals>
----- Practically Complete -----
----- Plate High ----
Related
15/08/2023
5
depends on your council, some 1 day some 14 days