Timeline
Feb 2010 - Found block of land in SOR
Mar 31 2010 - Signed plans with builder
May 14 2010 - land settlement
June 30 2010 - Signed first set of working drawings
July 20 2010 - PreStart Done
Aug 3 2010 - Prestart Variations Finalised
Sept 14 2010 - Building licence
Sept 24 2010 - Slabbed !!!
Oct 6th 2010 - Soakwelled ...
Oct 21th - Deliveries (briks n frames)
8th Nov 2010 - Termimesh On
9th Nov 2010 - Brick work started
15thDec 2010 - Brick Work complete
7th Jan 2011 - Roof started
1st Feb 2011 - Roof completed , BI
2nd Feb 2011 - Roof float
12thFeb 2011 - Ceilings & cornices doen
19Feb 2011 - White plaster done, windows n sliding doors done
25th Feb 2011 - Lockup
3rd March 2011 - Vanities, cupboards, brik acid wash, few internal doors, bath n accessories fitted
15 mar 2011 - Tiling in wet areas mostly done
18th mar 2011 - electricals done