I'm looking at your signatures and the time lines are very worrying. Is there any reason there was so so long between each thing, I can't believe it has taken so long. I'm in the Hunter and we were told it would take about 4 weeks to get the plans (we paid the deposit on 1/12/10 and still waiting) then 2 weeks in council, then 19 weeks building contract which Beechwood usually finish in about 14 weeks. Something seems to be way off here???
Way off is not the words for it. Our contract was for 23 weeks.....bad weather was to blame for that. But to get us started it took nearly 8 months from the time we put the deposit down to when the building started.
Do you have any tips or hints in hind sight - anything that you think may make it happen a little quicker?
and also, when we got our first tender - it was way too $$$ so we changed from the Hermitage to the Lake View lodge (which anyone can tell you that its virtually the same plan!)
Let me assure you that Beechwood have been ready for months - we should be starting by the end of the month - 10 months after paying the deposit.
Its been a bugger but we cant do anything about it.
Have you started yet??? And where are you building???
I would try ringing head office every second day, emailing and just generally keeping on top of whats going on.
Have you started yet??? And where are you building???
Have you started yet??? And where are you building???
Thanks for that. We're just waiting on the plans (supposed to be ready today) so we can approve them to send to council. Although we have a couple of changes to make. We'll be dealing with the Beresfield office as we're building at Bolwarra Heights.
We have storm water and tank hooked up to the house as of today.
Electrician is coming next week to hook up temporary electricity for the painters to paint.
Getting close now?!!
If there is anything you want to know let me know.
Ill be calling monday after a start date.
Just keep on there back but at the same time, once there after some infomation make sure you are very prompt with getting it back to them.
that was our problem. We thought our finance was all sorted, but turned out it had expired so had to do all the finance again (re valuations etc)
New to this forum, and we are building with Beechwood, we too are a little disappointed how long it takes, the process is so slow....
bascially we are building the The Merlot with the Terrazza in The Hills District of Sydney.
We started dealing with Beechwood in March last year 2010, Paid deposit May, Final Plans August, Submitted to council October. Hiccup in council
So getting very annoyed with Beechwood, they just dont seem to care and the stamp duty saving was spent on extra's on or in the house...
Please tell me it gets better and not worst.....
Anyway, their tender looks very attractive compare to the other builder (also a project home builder) we are dealing with. I am just wondering if there will be "surprises" after we pay them the deposit. What's your experience? Is their tender kind of final?
Thanks!
Jessica
House is going well.....have all stormwater and septic hooked up but still have no lights or paint......have got the go slow on at the moment(thats beechwood)....
At the time , they were fairly new, & their prices were reasonable.
Just letting you know that because we were on a tight budget, we hardly made any upgrades, the only thing we
did from memory was upgrade the stove & oven, the rest we went basic inclusions, the only thing we found
with BH was their "after Sales " service, they were reluctant to come out when called, also, the paint they use
is not washable, which means if you have young kids it's a real nightmare
the house still looks nice, and their site site costs at the time were reasonable.....having said that, we are
building our second house at the moment & decided to go with Westminster Homes as we liked their quality inclusions.
Good luck to you all.
Hi Jacknruby,
Just letting you know that we have exactly the same delima with Westminster Homes, we too were supposed to start afetr Xmas.....and nothing has happened as yet....hoping to start "benching " ( levelling ) the site this week....so don't despair...SLOW must be all the Builders' motto!
I am glad that I am not the only one...going through this pain. It is turning me off building. Funny thing is I think your right they are all the same, i was speaking to the council officer that accessed our plans and I was saying to him I hope I haven't made the wrong decision in choosing Beechwood cause at the moment I am second guessing our decision, and he was like nope they are the same at the end of the day.
I am just really worried, as I really cant afford the stamp duty if they dont have the foundations down by the end of March, means all our upgrades will need to be downgraded
594jessica- we are the same thought they are very reasonable for all the extras and changes as compared to other put project home builders, but I guess I will tell hopefully this week when I get our contract, I am guessing it will be blown out, here hoping not to much more then the tender, we did some serious changes to the floor plan, moved the Laundry, added a walkin pantry, amongst other things and it all adds up, my hubby and I were getted a little carried away at one stage has to pull the reins in, I was like we have even started with the internals yet.......
Glad I found this site.....and can share my experiences and see I am not the only one experience stress.....
Do not despair!!!
Just to let you know you're not alone, the building company we are with told us from the beginning that our land comply's with comply & development (meaning we don't have to be approved thru council we can go thru a certifier which is quicker ), this was way back in June, we waited for all the paperwork to be done, after submission to the certifier in September, we get a phone call telling us oooops sorry we made a mistake, we have to resubmit & go thru council
With regards to your stamp duty, I suggest you hassle them till there's no tomorrow, cos you are the one who stands to benefit from this not them, so be firm but nice & keep calling, sending emails till you finally get what you want....don't stress, enjoy this time ( I know...
easily said than done
Got the contract after numerous follow ups, was almost ready to tell them to shove it, I just dont understand sometimes, you are spending so much money and they just couldnt give 2 hoots.....anyways the colour appointment made us change our feelings as the girl was so good and yep spent another $4k
Lucky we signed the contract this week as as of the 1 Jan the Merlot has increased another $4,000.00 but we were still in the 120 tender period (Thank Goodness) so instead of us coping the price hike we just spent it in the colour studio
Got to push the bank now for that letter of commencement! Wish me luck!
Regards for now...
Once they have the letter of commencement it took them about 4 weeks before they started.
Hopefully you don't have the rain that we had when we started
We now have septic and all stormwater hooked up. The painter started Thursday....then the electrician
should be in as soon as he is finished
Getting close now but has been a long and drawn out process
Will definately not do it again
Will add new photos as soon as I can get into the house
Thanks...
we are allowing $5k - we will have a fair few exterior lights though.
We too are having 50 downlights , but we're building with Westminster Homes & like you all, we have to go thru Costas. We got them to give us a quote that went in the contract & for 50 downlights they quoted us $5,500.00.... ( they're not cheap, I know )....Just one thing I would like to advise you all, DO NOT get normal downlights as they emit an enormous amount of heat and use up HEAPS of energy, ....Instead, get LED downlights, they're more expensive initially, but they use less power, emit a minimum amount of heat, are brighter and last alot longer than conventional ones, How do I know this you ask? My husband is an Electrical Engineer
Thanks for your replys...just a couple of ??
Acre-Is Costa's just doing the wiring and and have you engaged the private electrician? We have a friend who is a sparky but he is always so busy and thought might just be easier to get them done by Costas but now I am hearing the cost its a little freaky.....
Springtime - is the quote for $5k for LED Downlights? we have been to some light stores and they are recommending Compact Flouro Downlights (a lot cheaper and only use 9w of power LED use about 5W) but you can also buy LED globes for the CF's also not cheap mind you like $80 globe but guaranteed not to blow for 15 years, if a LED blows you have replace the whole downlight apparently.
DOes any know approx cost for costa's to put in extra power points?
Related
9/05/2023
4
go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages…
11/05/2023
1
Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow…