Browse Forums Building A New House Re: Who is building with Beechwood 1422Nov 01, 2011 7:20 pm Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1423Nov 01, 2011 7:37 pm McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 1426Nov 02, 2011 9:32 am Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1429Nov 02, 2011 9:35 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 1432Nov 03, 2011 12:00 pm Beechwood Homes Muscle Creek, Hunter Valley Paid Deposit Oct '10 Colour selec/Contract 17 Aug '11 28 days start- 12 Sept Bricks start 12 Jan Walk-through 12 April Re: Who is building with Beechwood 1433Nov 03, 2011 8:26 pm Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO Re: Who is building with Beechwood 1435Nov 04, 2011 8:00 pm McKeachies Run, Aberglasslyn Deposit paid 11th April Land registered 6th June Land settled 20th June Colour selections and contract signed 5th August Commencement letter received 26th September Re: Who is building with Beechwood 1438Nov 05, 2011 1:37 pm Our blog: http://durhamsadventure.blogspot.com Re: Who is building with Beechwood 1439Nov 05, 2011 3:10 pm Natandash, We moved into our last place with the interin cert Basically, they give you the interim cert with a list of things necessary to achieve the final cert. our last one was things like "landscaping, steps to the garage, handrail on steps etc" Building Beechwood Genesis Muscat (modified) Contract signed- April 19 Benching done- May 19 Piering done- June 27 Slab Plumbing- July 1st Slab poured- July 6th Frame finished- August 11 Re: Who is building with Beechwood 1440Nov 05, 2011 7:55 pm As we did all our our drainage (we did the connection from water tanks to the house and septic tanks to house) we only got interim as well, but really....we couldnt move in until all those things were complete were complete as we didnt have water Our Acreage Build The Lakeview Lodge - Beechwood Homes 01/04/10 YES 2010 - Deposit paid 23/09 - PCI CANCELLED 28/09 - PCI - will it happen.-18 months later 07/10/11 - ITS OURS..WOOHOO go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110570 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11035 |