Wow. That's only 3 days work. At that rate will be finished in no time.
Browse Forums Building A New House Re: Who is building with Beechwood 13301Sep 07, 2016 8:27 pm 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 13303Sep 08, 2016 5:31 pm 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 13311Sep 09, 2016 9:38 am Deposit paid 09/02/14 Plans received 26/04/14 Land registered 01/08/2014 Settled on land 18/08/2014 Plans to council 20/08/2014 http://verdelhofourtwist.blogspot.com.au/ Who is building with Beechwood 13312Sep 10, 2016 7:24 am 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 13314Sep 10, 2016 7:44 am Moscato5 This is our place since Wednesday. Looking good from a distance. Loving the colour. Seems they now need to wait on more bricks to be delivered. Hopefully not too much of a hold up Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Yay... Progress! Our First Home Eagles Nest Wadalba Central Coast NSW http://kellyandlorenzo.blogspot.com.au/ Re: Who is building with Beechwood 13315Sep 10, 2016 7:53 am Moscato5 This is our place since Wednesday. Looking good from a distance. Loving the colour. Seems they now need to wait on more bricks to be delivered. Hopefully not too much of a hold up Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looking really good! Love the brick colour. Deposit paid 09/02/14 Plans received 26/04/14 Land registered 01/08/2014 Settled on land 18/08/2014 Plans to council 20/08/2014 http://verdelhofourtwist.blogspot.com.au/ Re: Who is building with Beechwood 13316Sep 10, 2016 11:30 am Moscato5 This is our place since Wednesday. Looking good from a distance. Loving the colour. Seems they now need to wait on more bricks to be delivered. Hopefully not too much of a hold up Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Yay!!! Looks great. Fingers crossed for a speedy brick delivery!!! Re: Who is building with Beechwood 13317Sep 11, 2016 9:43 am U would think they would delivery all the bricks in one hit. Looks great Moscato5 Lakeview 27 - Beechwood 12/2015 Deposit 7/2016 Council/Certifier 8/8/2016 Colour Appointment & Contract Signed 11/08/2016 Work started with Surveyors pegging out Lakeview 27 - Beechwood 12/15 Deposit 7/16 Council/Certifier 8/16 Colour Appointment Re: Who is building with Beechwood 13318Sep 11, 2016 10:27 am Moscato5 This is our place since Wednesday. Looking good from a distance. Loving the colour. Seems they now need to wait on more bricks to be delivered. Hopefully not too much of a hold up Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Looking great!! What brick colour did you go with? Buildingabetterhome.blogspot.com.au Land deposit - Oct 14 Deposit - Jan 16 Land registered - June 16 Settlement - July 16 Colour selection and approval -Sept 16 Slab- Nov 16 Frame - Dec 16 Re: Who is building with Beechwood 13319Sep 11, 2016 10:57 am Lakeview27 our block is only small and because both neighbours are also building there's very limited space. Grace33 it's Austral Whitsunday Orpheus. It was our first choice brick, we then ummed and arrrred about it, changed to multiple others but landed back at it. And I know it's only early days and it's not complete or washed, but I'm so glad we did. Loving it already. 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 13320Sep 11, 2016 8:17 pm Moscato5 Lakeview27 our block is only small and because both neighbours are also building there's very limited space. Grace33 it's Austral Whitsunday Orpheus. It was our first choice brick, we then ummed and arrrred about it, changed to multiple others but landed back at it. And I know it's only early days and it's not complete or washed, but I'm so glad we did. Loving it already. We went with Urban One - Chiffron go upvc window frames ensure insulation under colorbond. not just sarking, lighter color roof also not sure if you have seen this viewtopic.php?t=5823 last couple of pages… 4 110758 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 11116 |