Browse Forums Building A New House Re: Builder threatening to charge interest on incomplete hou 5Apr 16, 2010 2:06 pm View our blog at: http://room4acubby.blogspot.com/ Re: Builder threatening to charge interest on incomplete hou 7Apr 16, 2010 2:52 pm 12 March 2010 - Land titles received 3 April 2010 - Signed building contract 14 April 2010 - Prestart 28 April 2010 - Loan approved 30 June 2010 - Slab completed 27 August 2010 - Brickwork completed 22 September 2010 - Roofing completed 30 September 2010 - Internal walls plastered 12 October 2010 - Lock Up 19 November 2010 - PCI 26 November 2010 - Handover 29 December 2010 - Moved In https://forum.homeone.com.au/viewtopic.php?f=31&t=32584 Re: Builder threatening to charge interest on incomplete hou 8Apr 16, 2010 3:17 pm aLLaNNa1 For instance, in our site costs they included an $800 allowance for "builder to repair and/or replace kerbs and/or footpath if damaged during construction". Now if the damage was caused by the builder during the construction period, why would I have to pay for the damage? That's crazy! I think you'll find that the builder has to pay a bond to the local Council to safeguard against damage. Built a Tribeca 44 with the Big M Sales Accept 15/06/09, Contract Signed 24/09/09, Site Start 23/11/09, Slab 11/12/09, Frame 12/01/10, Roof 20/01/10, Lock-up 30/03/10, Fixing 30/04/10, Handover 27/08/10. Hi, did you get any money from insurance? if you did, does it match what you've already paid the builders? 3 9440 If you already have a contract, is the inspection cost stated in there? If not they would be forced to issue you a variation which you could of course object to. 12 25826 |