Browse Forums Building A New House 1 Apr 06, 2010 4:58 pm Finally, Titles have been issued today by Land gate. Everything is progressing well. I have prestart this friday. Thanks for all the support so far. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 Re: WOW - Titles Issues - Northerly Estate Stage 3 Piara wat 2Apr 06, 2010 5:00 pm Congrats on titles. One of the first people out here that I know of that got your titles about when they said they would be ready Built with RedInk Custom 5000 Key Handover 15/12/2009 Re: WOW - Titles Issues - Northerly Estate Stage 3 Piara wat 3Apr 06, 2010 5:39 pm ref_kt Congrats on titles. One of the first people out here that I know of that got your titles about when they said they would be ready Thanks. To be truthful, i was also surprised, when i was told that the titles have been issued. Its good to see it happen as per initial forecast. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 Re: WOW - Titles Issued - Northerly Estate Stage 3 Piara wat 4Apr 07, 2010 9:18 pm congratulations!!! your so lucky titles early, im over the road in newhaven and mine are nearly 2months late hope prestart goes well and build goe smoothly When times get tough build a house...Our second build Re: WOW - Titles Issued - Northerly Estate Stage 3 Piara wat 5Apr 07, 2010 10:19 pm sharky55_shan congratulations!!! your so lucky titles early, im over the road in newhaven and mine are nearly 2months late hope prestart goes well and build goe smoothly Thanks for the wishes. I will let you know, how i go with prestart in 2 days. Land - Northerly Estate, Piara Waters Titles Issues 05 April 2010 Building with Ross North Homes Prestart Completed 12 April 2010 Finance Approved 01 May 2010 Slab down 29 May 2010 Frame Completed 28 June 2010 Roof Completed 22 July 2010 Lockup 12 August 2010 PCI 24 Sep 2010 Handover 08 Oct 2010 Building Thread https://forum.homeone.com.au/viewtopic.php?f=31&t=32295&start=0 Re: WOW - Titles Issued - Northerly Estate Stage 3 Piara wat 6Apr 07, 2010 10:25 pm Congrats mate, let the fun begin Congratulations! Nice to put that to bed before christmas, now you can relax 3 7179 Not unless you have managed to put it as a special condition into the contract somehow. 1 6155 The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is. 1 8706 |