Hey guys/gals,
With my build dragging out a bit, I'm looking at doing a calc to figure out my TRUE end date for build.
The Victorian HIA New Homes Contract - Schedule 1 (page 6) says the following:
xxx Days including the following esimates for delays:
- Inclement weather....... AAA days
- Weekends, holidays, etc ...... BBB days
- Other gratuitous reasons (XMAS, Easter) ...... CCC days
NOW,
Does this mean that the the end to end contract term (including weather, weekends and gratuities) is xxx Days
OR
Is the total term xxx Days + AAA + BBB + CCC meaning a total end to end contract term?
I'm not mentioning the builder as it's irrelevent in this situation.