Browse Forums Building A New House Re: Lock Up To Handover - How Long 2Mar 29, 2010 10:48 am Our SS reckoned 5-6 weeks... I'd love to find out he was right 4 more weeks before we know ... built a Promenade with Clarendon. viewtopic.php?f=31&t=25104 20-10-09 - excavation and piering completed ... 12-04-10 - Basins fixed. Connecting to the electrical grid 23-04-10 - PCI 07-05-10 - HANDOVER! Re: Lock Up To Handover - How Long 3Mar 29, 2010 12:11 pm I got to lock-up stage end Jan, fittings end Feb. PCI in early April. Re: Lock Up To Handover - How Long 4Mar 29, 2010 3:54 pm We got to lockup Feb 16th. Handover April 7th. I think it depends on the size of your builder... bigger builders tend to take longer and smaller builders not as long as thy don't have as many jobs happening at once. Our new home - viewtopic.php?f=31&t=31696 Our new house - moved in but so much more to do! https://forum.homeone.com.au/viewtopic.php?f=31&t=31696&p=442009#p442009 Re: Lock Up To Handover - How Long 5Mar 29, 2010 8:04 pm Our builder has said 10-12 weeks from lock-up to get to practical completion, an extra 2 weeks to do their own final checks, PCI, then another 2 weeks to fix any things that arise from PCI. So 14-16 weeks. 1 4678 Congratulations! Nice to put that to bed before christmas, now you can relax 3 7134 What? It's a lighting question, the control joint is only needed at 12m centres, a bulkhead or change of direction will suffice as a 'break' in the ceiling, just make… 8 8551 |